Pustynnoe Phase 3 (Dolinnoe)
2020-2021
Location
Kazakhstan, Karaganda region
Capacity
Up to 2.5 million tons of ore per year
Client
АО АК "Алтыналмас"
00:00 / 00:00
Currently, the project’s third phase has been commissioned and brought up to design performance

This time, Pustynnoye was supplemented with new facilities to process ore from Dolinnoye mine.

A new 220kV substation was to be built due to increased loads on the existing power grid and anticipated expansion of production. In addition, a number of hydraulic facilities were designed and built, including a new containment pond and tailings storage facility (TSF).


Currently, the project’s third phase has been commissioned and brought up to design performance

This time, Pustynnoye was supplemented with new facilities to process ore from Dolinnoye mine.

A new 220kV substation was to be built due to increased loads on the existing power grid and anticipated expansion of production. In addition, a number of hydraulic facilities were designed and built, including a new containment pond and tailings storage facility (TSF).


Project implementation
1.

Construction of a crushing and screening complex

2.

Crushed ore stockpile

3.

Plant building with crushing, gravity concentration, reagents and other areas to operate the new plant

4.

New 220kV substation

5.

New containment pond 

6.

Tailings storage facility (TSF)

EPC
contract
silver
FIDIC book