Processing MMMF Aksu, Bestobe, Zholymbet

Project implementation: 2016-2018
Project implementation: 2016-2018. Capacity: 7 million tons of MMMF per year (total capacity of three plants) Contract on development of a feasibility study and an EPC agreement.
FACILITIES ENGINEERING AND CONSTRUCTION
Aksu open pit
  • Gold processing plant:
- MMMF supply unit;
- Grinding and classification site;
- Sorption leaching site;
- Product electrolysis and melting building;
- Elution, regeneration and acid washing building;
- Chemicals preparation section.
  • Oxygen station building;
  • Conveyor loading ramp;
  • Administrative and amenities building (AAB);
  • Closed inventories warehouse;
  • Coal-fired boiler house;
  • Main highly toxic substances warehouse;
  • Open inventories warehouse;
  • Substation;
  • New tailings facility with main slurry line;
  • Gathering pond with clean water mains.
Bestobe open pit
  • Processing plant:
- MMMF supply unit;
- Grinding and classification site;
- Sorption leaching site;
- The site of tailings from sorption leaching thickening;
- The site of neutralization of cyanide tailings with their further storage in the tailings facility.
  • Oxygen station building;
  • Conveyor loading ramp;
  • Administrative and amenities building;
  • Open inventories warehouse;
  • Chemicals warehouse;
  • Coal-fired boiler house;
  • Open warehouse;
  • Substation;
  • Highly toxic substances warehouse;
  • Thickener;
  • New tailings facility with main slurry line;
  • Gathering pond with clean water mains
Zholymbet open pit
  • Processing plant:
- MMMF supply unit;
- Grinding and classification site;
- Sorption leaching site;
- The site of tailings from sorption leaching thickening;
- The site of neutralization of cyanide tailings with their further storage in the tailings facility.
  • Oxygen station building;
  • Conveyor loading ramp;
  • Administrative and amenities building;
  • Open inventories warehouse;
  • Chemicals warehouse;
  • Coal-fired boiler house;
  • Open inventories warehouse;
  • Substation;
  • Highly toxic substances warehouse;
  • Thickener;
  • New tailings facility with main slurry line;
  • Gathering pond with clean water mains.